Logo
  • Home
  • About Us
    • Aim and Scope
    • Research Area
    • Impact Factor
    • Indexing
  • For Authors
    • Authors Guidelines
    • How to publish paper?
    • Download Paper format
    • Submit Manuscript
    • Processing Charges
    • Download Copyrights Form
    • Submit Payment-Copyrights
  • Archives
    • Current Issues
    • Past Issues
    • Conference Issues
    • Special Issues
    • Advance Search
  • IJARIIE Board
    • Join as IJARIIE Board
    • Advisory Board
    • Editorial Board
    • Sr. Reviewer Board
    • Jr. Reviewer Board
  • Proposal
    • Conferece Proposal
    • Special Proposal
    • Faqs
  • Contact Us
  • Payment Detail

Call for Papers:Vol.11 Issue.4

Submission
Last date
28-Aug-2025
Acceptance Status In One Day
Paper Publish In Two Days
Submit ManuScript

News & Updates

Submit Article

Dear Authors, Article publish in our journal for Volume-11,Issue-4. For article submission on below link: Submit Manuscript


Join As Board

Dear Reviewer, You can join our Reviewer team without given any charges in our journal. Submit Details on below link: Join As Board


Paper Publication Charges

IJARIIE APP
Download Android App

For Authors

  • How to Publish Paper
  • Submit Manuscript
  • Processing Charges
  • Submit Payment

Archives

  • Current Issue
  • Past Issue

IJARIIE Board

  • Member Of Board
  • Join As Board

Downloads

  • Authors Guidelines
  • Manuscript Template
  • Copyrights Form

Android App

Download IJARIIE APP
  • Authors
  • Abstract
  • Citations
  • Downloads
  • Similar-Paper

Authors

Title: :  The Implementation of Earned Value Management (EVM) in Cost and Time Control of a Road Improvement Project
PaperId: :  27040
Published in:   International Journal Of Advance Research And Innovative Ideas In Education
Publisher:   IJARIIE
e-ISSN:   2395-4396
Volume/Issue:    Volume 11 Issue 4 2025
DUI:    16.0415/IJARIIE-27040
Licence: :   IJARIIE is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Author NameAuthor Institute
Ir. Rezi Munizar, S.T., M.T.Ratu Samban University
Ir. Benny Dwika Leonanda, M.T., IPM., ASEAN Eng.Andalas University

Abstract

Civil Engineering
Project Performance, Earned Value Management (EVM), Cost & Time Management of Construction Projects
The construction of road infrastructure in Indonesia continues to progress as a form of the Government’s responsibility in providing safe and comfortable mobility facilities for the public. The increasing intensity of construction projects, particularly road development, is often faced with various challenges, one of which is project delays. These delays can cause significant losses to both contractors and project owners, thereby highlighting the need for effective project management to address such issues. One method that can be used for cost and time control in projects is the Earned Value Management (EVM) method. Earned Value Management is an integrated approach to controlling project cost and schedule by estimating the cost of the work that has been completed. This method can be used to assess the current condition of a project based on performance elements at the time of monitoring. This study was conducted by examining a road improvement project in Mukomuko Regency, Bengkulu Province. The results showed that the project performance condition could be classified as “Very Good,” as indicated by the analysis of SV (Schedule Variance), SPI (Schedule Performance Index), CV (Cost Variance), and CPI (Cost Performance Index), where none of the values were negative or below zero (<0). This indicates that the project activities were carried out faster than scheduled, the work met expectations or was on time, and even exceeded planned targets during certain weeks. The estimated cost to complete the project is predicted to be IDR 25,***,***,***. The project is expected to be completed on time within 25 weeks. It is also predicted to yield a profit of IDR 37,***,*** or approximately ± 0.14%. Although this is not a significant profit margin, the project can still be considered successful and not financially detrimental.

Citations

Copy and paste a formatted citation or use one of the links to import into a bibliography manager and reference.

IJARIIE Ir. Rezi Munizar, S.T., M.T., and Ir. Benny Dwika Leonanda, M.T., IPM., ASEAN Eng.. "The Implementation of Earned Value Management (EVM) in Cost and Time Control of a Road Improvement Project" International Journal Of Advance Research And Innovative Ideas In Education Volume 11 Issue 4 2025 Page 166-171
MLA Ir. Rezi Munizar, S.T., M.T., and Ir. Benny Dwika Leonanda, M.T., IPM., ASEAN Eng.. "The Implementation of Earned Value Management (EVM) in Cost and Time Control of a Road Improvement Project." International Journal Of Advance Research And Innovative Ideas In Education 11.4(2025) : 166-171.
APA Ir. Rezi Munizar, S.T., M.T., & Ir. Benny Dwika Leonanda, M.T., IPM., ASEAN Eng.. (2025). The Implementation of Earned Value Management (EVM) in Cost and Time Control of a Road Improvement Project. International Journal Of Advance Research And Innovative Ideas In Education, 11(4), 166-171.
Chicago Ir. Rezi Munizar, S.T., M.T., and Ir. Benny Dwika Leonanda, M.T., IPM., ASEAN Eng.. "The Implementation of Earned Value Management (EVM) in Cost and Time Control of a Road Improvement Project." International Journal Of Advance Research And Innovative Ideas In Education 11, no. 4 (2025) : 166-171.
Oxford Ir. Rezi Munizar, S.T., M.T., and Ir. Benny Dwika Leonanda, M.T., IPM., ASEAN Eng.. 'The Implementation of Earned Value Management (EVM) in Cost and Time Control of a Road Improvement Project', International Journal Of Advance Research And Innovative Ideas In Education, vol. 11, no. 4, 2025, p. 166-171. Available from IJARIIE, http://ijariie.com/AdminUploadPdf/The_Implementation_of_Earned_Value_Management__EVM__in_Cost_and_Time_Control_of_a_Road_Improvement_Project_ijariie27040.pdf (Accessed : 12 July 2025).
Harvard Ir. Rezi Munizar, S.T., M.T., and Ir. Benny Dwika Leonanda, M.T., IPM., ASEAN Eng.. (2025) 'The Implementation of Earned Value Management (EVM) in Cost and Time Control of a Road Improvement Project', International Journal Of Advance Research And Innovative Ideas In Education, 11(4), pp. 166-171IJARIIE [Online]. Available at: http://ijariie.com/AdminUploadPdf/The_Implementation_of_Earned_Value_Management__EVM__in_Cost_and_Time_Control_of_a_Road_Improvement_Project_ijariie27040.pdf (Accessed : 12 July 2025)
IEEE Ir. Rezi Munizar, S.T., M.T., and Ir. Benny Dwika Leonanda, M.T., IPM., ASEAN Eng., "The Implementation of Earned Value Management (EVM) in Cost and Time Control of a Road Improvement Project," International Journal Of Advance Research And Innovative Ideas In Education, vol. 11, no. 4, pp. 166-171, Jul-Aug 2025. [Online]. Available: http://ijariie.com/AdminUploadPdf/The_Implementation_of_Earned_Value_Management__EVM__in_Cost_and_Time_Control_of_a_Road_Improvement_Project_ijariie27040.pdf [Accessed : 12 July 2025].
Turabian Ir. Rezi Munizar, S.T., M.T., and Ir. Benny Dwika Leonanda, M.T., IPM., ASEAN Eng.. "The Implementation of Earned Value Management (EVM) in Cost and Time Control of a Road Improvement Project." International Journal Of Advance Research And Innovative Ideas In Education [Online]. volume 11 number 4 (12 July 2025).
Vancouver Ir. Rezi Munizar, S.T., M.T., and Ir. Benny Dwika Leonanda, M.T., IPM., ASEAN Eng.. The Implementation of Earned Value Management (EVM) in Cost and Time Control of a Road Improvement Project. International Journal Of Advance Research And Innovative Ideas In Education [Internet]. 2025 [Cited : 12 July 2025]; 11(4) : 166-171. Available from: http://ijariie.com/AdminUploadPdf/The_Implementation_of_Earned_Value_Management__EVM__in_Cost_and_Time_Control_of_a_Road_Improvement_Project_ijariie27040.pdf
BibTex EndNote RefMan RefWorks

Number Of Downloads


Last download on 7/12/2025 6:32:32 AM

Save in Google Drive

Similar-Paper

TitleArea of ResearchAuther NameAction
COST AND TIME CONTROL ANALYSIS OF THE NEW OPERATIONAL BUILDING CONSTRUCTION PROJECT AT FATMAWATI SOEKARNO AIRPORT BENGKULUCivil EngineeringBuyung Mantap Download
The Implementation of Earned Value Management (EVM) in Cost and Time Control of a Road Improvement ProjectCivil EngineeringIr. Rezi Munizar, S.T., M.T. Download
Predicting Cement Hydration and Mechanical Performance with Machine Learning and Supplementary Cementitious MaterialsConstruction EngineeringRAJAT PANDEY Download
Use of Rice Straw Ash as Cement Replacement Material in ConcreteCivil EngineeringV. John Sundar Raj Download
How Plastic Waste can be Utilized for the Stabilization of Soils for Road Pavement ConstructionCivil EngineeringAper E. Zava Download
ENHANCING THEORETICAL LEARNING IN ENGINEERING EDUCATION THROUGH AUGMENTED REALITYCIVIL ENGINEERING FELIX BIKETI Download
AUGMENTED REALITY AS A TOOL FOR PRACTICAL SKILLS DEVELOPMENT IN BUILDING AND CIVIL ENGINEERING PROGRAMMESCIVIL ENGINEERING FELIX BIKETI Download
EXPERIMENTAL INVESTIGATION AND ANALYSIS OF BAMBOO FRAMECIVIL ENGINEERINGMAHESWARI K Download
PARTIAL REPLACEMENT OF CEMENT USING SUGARCANE BAGGASE ASH TO ENCHANCE THE STRENGTH OF CONCRETECivil EngineeringDhanraj Balu Vitekar Download
HEC-RAS BASED HYDRAULIC MODELING OF PUS RIVER FOR FLOOD MANAGEMENTCivil Engineering Kunal D Manwar Download
Sewage water treatment plantCivil engineeringBhoopesh Ghorse Download
To increase the compressive strength of concrete by replacing fine aggregate with shredded steel wasteCivil EngineeringChandan Kumar Download
Analysis and Design of E-Waste Management: Enhancing Concrete with Recycled E-Wastecivil Engineering Palak Tomar Download
SUBGRADE STABILIZATION OF EXPANSIVE SOIL USING LIQUID POLYMERCivil engineering Deepak Singh Download
Study of Physical Characteristics of Self-healing ConcreteCivil EngineeringAbhay Singh Download
12
For Authors
  • Submit Paper
  • Processing Charges
  • Submit Payment
Archive
  • Current Issue
  • Past Issue
IJARIIE Board
  • Member Of Board
  • Join As Board
Privacy and Policy
Follow us

Contact Info
  • +91-8401209201 (India)
  • +86-15636082010 (China)
  • ijariiejournal@gmail.com
  • M-20/234 Ami Appt,
    Nr.Naranpura Tele-Exch,
    Naranpura,
    Ahemdabad-380063
    Gujarat,India.
Copyright © 2025. IJARIIE. All Rights Reserved.